On July 17, all four westbound lanes of I-26 opened in their final configuration. They run from U.S. 64 in Henderson County to Brevard Road in Asheville, and that includes the climb past Long Shoals Road up toward the Blue Ridge Parkway bridge. The eastbound side was scheduled to catch up last week. NCDOT closed I-26 East between I-40 and Long Shoals Road overnight on October 7 and October 8 so crews could finish the new lanes from the Pond Road bridge to Exit 37. Opening was set for right after that.
Once those eastbound lanes are open, a drive between Arden and I-40 has four lanes in both directions. The thing that hasn't changed is the number on the speed limit signs. Ordinances already set 65 mph for the stretch through Arden, but the 55 mph work-zone limit stays until the project is complete or NCDOT rescinds that limit. NCDOT's published estimates of when the project will be complete are as much as nine months apart.
The order the road came back
The project started in 2019 and runs from U.S. 64 in Hendersonville to Brevard Road in Asheville. Here is the order of the last few milestones for anyone driving in and out of Exit 37 or Exit 40:
- July 17, 2026. All four westbound lanes open from Exit 49 to Exit 33.
- October 7 and 8, 2026. Overnight closures from 8 p.m. to 6 a.m. on I-26 East between I-40 and Long Shoals Road for final work on the new eastbound lanes.
- Later in October, dates not yet announced. Two lanes of the French Broad River bridge close during the day so crews can seal the bridge.
- This winter. The new Exit 35 interchange at Frederick Law Olmsted Way is due to be finished.
When the eastbound work is done, that side will have four lanes for about 12 miles, from I-40 to U.S. 25 at Exit 44, and three lanes from there to U.S. 64 at Exit 49. We found reporting from October 7 and 8 saying the lanes were about to open, but nothing yet confirming the actual opening day. If eastbound traffic past Pond Road still looks different than expected, that's the reason.
Westbound drivers have had the full road since mid-July. That hill had been the slow spot for years. NCDOT contract resident engineer Luke Middleton told WLOS on opening day:
"For the longest time, there's been a slowdown right there at Long Shoals and the Parkway with a lot of the truck traffic having a tough time getting up the hill."
Why every sign still says 55
According to NCDOT Western Communications Manager David Uchiyama, as reported in a WLOS Ask 13 segment published October 6, the higher limits have already been approved. The approved limits are below, next to what's posted today.
| I-26 segment | Posted today | Approved for after the work zone ends |
|---|---|---|
| I-40 to Brevard Road, both directions | 55 mph work zone | 60 mph |
| Brevard Road to Airport Road, both directions | 55 mph work zone | 65 mph |
The second row covers the Arden drive: Long Shoals Road at Exit 37 and Airport Road at Exit 40, plus the Parkway bridge between them. That segment is getting the biggest increase anywhere in the Buncombe County section, 10 mph over today's limit. Uchiyama said the 55 mph work-zone limit stays until the project is complete or the work-zone limit is rescinded.
Much of the remaining work is detail that's easy to miss from the driver's seat. When westbound opened in July, NCDOT said diamond grinding to smooth the surface, new pavement markings and concrete joint work still needed more overnight closures. It also said about six months of construction remained west of the Blue Ridge Parkway bridge. Six months from mid-July puts that work into January 2027.
The finish date depends on which NCDOT number you read
That's where the estimates split. NCDOT's I-26 widening project page still gives Fall 2026 for completion and $531 million for cost. The same page says it was last updated April 9, 2025, before most of the past year's milestones.
In June 2025, an Asheville Watchdog column quoted an NCDOT spokesperson giving July 1, 2027 as the revised completion date for the Buncombe County contract. The column described the project as costing $534 million and said the target had already moved from 2024 to 2025 to 2026. In January 2026, WLOS reported that NCDOT expected the widening to be finished in 2027.
Put the three side by side and the Fall 2026 date looks like the outlier. July's six-months-of-work estimate, the winter target for Exit 35 and the 2027 completion year all line up with each other. None of these sources says when the 65 mph signs will go up between Brevard Road and Airport Road. Based on the published timelines, the 55 mph work zone looks set to last through this winter, and possibly well into 2027.
Exit 35 is built for the trip into Asheville
The last major piece is the one Arden drivers may notice first. NCDOT's project page for the interchange describes Exit 35 as a new access road from I-26 to Frederick Law Olmsted Way East, which connects to N.C. 191. The page links the road to Biltmore Park West and the Pratt & Whitney Manufacturing Center. The chosen design uses left-side exit and entrance ramps, and they serve westbound, Asheville-bound traffic only.
That design explains another answer from the Ask 13 segment. A viewer asked whether trucks would be kept out of the left lane on the widened road. Uchiyama said the interchange design rules that out near Exit 35, because trucks need to reach the upcoming left-hand exit for I-26 West. NCDOT will watch truck movements and traffic flow along the corridor after construction ends to decide whether any changes are justified.
For someone leaving Arden at Long Shoals or Airport Road and heading north, the left lane past the Parkway bridge will keep carrying trucks that are lining up for Exit 35. For the same reason, there's no matching Exit 35 ramp for drivers coming home southbound from Asheville. Exits 37 and 40 stay the way off the interstate into Arden.
Before the French Broad bridge closures
NCDOT hasn't announced dates for the daytime closures of two lanes on the French Broad River bridge, only that they'll happen later this month. The bridge is north of the Arden exits, between Brevard Road and I-40, so it affects any trip toward Asheville by interstate. During last week's eastbound overnight closures, NCDOT sent drivers onto I-40 East to Hendersonville Road at Exit 50, then south to Long Shoals Road or Airport Road. That route used surface streets Arden residents already know well. NCDOT hasn't said whether the bridge work will come with a detour of its own.
When the bridge sealing is finished, Exit 35 opens and the work-zone limit is lifted, the approved limits take over: 65 mph from Airport Road to Brevard Road and 60 mph from Brevard Road to I-40. None of the sources gives a date for that.
How long the drive to Exit 37 or Exit 40 takes matters when you're choosing a street in Arden, and it'll shift as this project wraps up. If you're thinking about buying or selling in south Buncombe and want to talk through how the I-26 changes affect getting around from different parts of Arden, Rebecca Lafunor is happy to sit down with you. Request a Free Consultation.